Retainage in construction, explained

By Reese Calloway, editor · numbers recomputed with the calculators on this site

Retainage is money you have earned but will not be paid until later. On thin margins it can hold back more than your whole profit on the job.

What retainage is

Retainage (or retention) is a percentage of each progress payment that the owner or GC holds back until the work, or a defined part of it, is complete. It gives the payer leverage to get punch-list and closeout items finished. The percentage is set by the contract, often 5% or 10%, and some contracts reduce it once the job is half complete.

How it is calculated

Retainage held = billed amount × retainage %. On each pay application you bill the work completed, and the payer deducts retainage from what it pays. The held amount accumulates until release.

When it is released

Usually at substantial or final completion, after closeout documents (lien waivers, warranties, O&M manuals, as-builts). Subcontractors often wait for the GC to be released by the owner. Pay-when-paid clauses can make that wait longer.

State rules

Many states have prompt-payment or retainage statutes that cap the percentage, set release deadlines or require interest on late retainage, and the rules often differ for public and private work. Check your state’s statute and your contract before you sign.

What it does to cash flow

If your profit on the job is smaller than the retainage held, the job can be cash-negative until release. Price financing cost into long jobs, and track retainage receivable separately from ordinary receivables.

$240,000 subcontract, 10% retainage, billed over 6 months

Monthly billing$40,000
Retainage held each month$4,000
Paid each month$36,000
Retainage held at completion$24,000
Profit on the job at a 10% margin$24,000
Cash still owed to you at completion$24,000

Illustrative numbers, rounded. They are a teaching example, not a quote or a market rate.

Common questions

What is 10% retainage?

The payer holds back 10% of each progress payment until the work is complete. On a $100,000 contract, $10,000 is held.

Is retainage the same as retention?

Yes. Retainage and retention describe the same thing.

Can retainage be reduced during the job?

Many contracts reduce it after a set percentage of completion. It is negotiated, and some states set rules.

When should a sub get retainage back?

When the contract says, commonly after the sub’s work is complete and accepted and closeout documents are in. Check state prompt-payment rules for deadlines.

Price it right. Run the free markup vs margin, labor burden, sales tax and escalation calculators, or build the whole number in the bid builder.

Education, not legal, tax or insurance advice. Contract terms, retainage and tax rules vary by state and contract; check your contract and your state’s rules.

Free download

The Bid & Markup Worksheet

Price a job from labor burden up: true cost per billable hour, materials with tax and waste, overhead, and a price set by margin, not markup.

You’ll get The Bid & Markup Worksheet right away. Free, unsubscribe in one click, and we never sell your email.